We have been suffering from significant shipping delays on fiber terminals. Our first order was suppose to be here by the first week in May and when I contacted the manufacturer they told me to wait until AUGUST! I'm not waiting. We did some quick reengineering and started installing what we could get last week. I will be turning on the first customer in the Aguilar node next week, slightly behind schedule. There will still be some gaps in Aguilar I need to fill but at least I will have customers testing the system. Thanks to everyone who has volunteered to be a tester!
Enough terminals for the rest of the year have been ordered and should be here in 6-8 weeks. I hope to finish Aguilar before that and wait to move on to Deer Creek and Salem Park after the terminals arrive.
John Bowcut
I was supposed to get a call about being a test customer. When will I get that call?
Glad to hear it! Can't wait for y'all to come to Deer Creek.